Cycle direction
New cycle routes in the district. Cycle lanes or two-way cycle streets are installed in 16th-district streets. Includes specific ground markings and signage installation.
Roads · Other
262k €
voted in the 2022 budget
The companies working on it
Contracts matched automatically to this project: check each contract’s object. Each line opens the contract.
ENT. DE TRAVAUX FAYOLLE ET FILSAménagement Cyclable Travaux Infra Sud/sud-ouest/bois Boulo lot 12021 · confirmed58€MEUROVIA ILE DE FRANCEAménagement Cyclable Travaux Infra Arrond Centre + Nd-ouest lot 2
2021 · confirmed46€METABL. DE BONNEUIL SUR MARNEAménagement Cyclable Travaux Infra Nd-est/sud-est/bois Vinc lot 3
2021 · confirmed37.4€MCOGELUM IDFAménagement Cyclable Travaux Epslt Arrond.centre/nord-ouest lot 5
2021 · confirmed23.6€MEIFFAGE ENERGIE SYSTEMES IDFAménagement Cyclable Travaux Epslt Nd-est/sud-est/bois Vinc lot 6
2021 · confirmed6€M
Other roads projects · 2022
Porte Maillot - Redevelopment17th7.1€MRue d'Aubervilliers - Éole-Évangile sector redesign19th1.2€MGaité Montparnasse block - Avenue du Maine roadway works14th1.1€MVarious streets - Beautify your neighbourhood Choisy13th1.1€MArrondissement 16 · View on OpenStreetMap ↗
Amount voted, not final spending: the published accounts do not systematically give the closing balance. Source: CA appendix 2022 · page 48 ↗