Swimming pool · 13e
Piscine Dunois
565k €
ordered from companies for this place — contract ceilings, not spending
What the City funds here
Works and renovation
565k €
contract ceiling · 2015
2 contracts signed in 2015, 565 k € ceiling
A contract amount is a ceiling, not spending: what was actually paid on it is not published by the City.
What the Paris Council said about it
2 moments found in the 2 deliberations read. Each line opens the document.
DECEMBER 2003Second phase of works, one year later, technical renovationThe Council approves the principle of three new procurement contracts and authorizes the Mayor to enter into them, for electrical work, filtration, and plumbing.NOVEMBER 2002First known works, safety and water treatmentThe Council approves the principle of three procurement contracts and authorizes the Mayor to enter into them, for bringing the fire alarm up to code and treating the filter water (chlorine).Same kind