Staff-area redesign and central-hall glass-roof repair
In 2022, the City of Paris budgeted €99k for "Staff-area redesign and central-hall glass-roof repair" (, 18th arrondissement). Source: City of Paris, localised investments in the administrative account, data as of 9 February 2026.
Staff-premises fit-out and central-hall glass-roof repair. The works cover interior renovation of offices or staff rest rooms. Outside, the glass roof above the central hall is repaired to ensure water-tightness and safety.
Administration · Other
The companies working on it
Contracts matched automatically to this project: check each contract’s object. Click a line to open the contract.
ALB-BAT GROUPETRX Restruct. Bureaux et Locaux Sociaux Cimetière Bagneux2022 · confirmed432k €ATATRX Réaménagement Locaux Sociaux Atelier Foch
2021 · confirmed424k €ATARénovation Locaux Sociaux Atelier 17
2021 · confirmed316k €ENGIE ENERGIE SERVICESModernisation des Locaux Sociaux et Ventilat°de L'ascenseur
2022 · confirmed89k €ATELIER D'ARCHITECTURE C'EST ELLESMaîtrise d’œuvre Restruct Locaux Sociaux centre(s) Sportif Carpentier Masse
2022 · confirmed64k €
Other administration projects · 2022
Day-care centre Garancière - Restructuring works6th907k €11th district Town Hall - Facade refurbishment and roofing11th860k €5th district Town Hall - Safety-accessibility master plan5th851k €Window frames, attic insulation, floor refurbishment, Town Hall facade refurbishment20th759k €Arrondissement 18 · View on OpenStreetMap ↗
Amount voted, not final spending: the published accounts do not systematically give the closing balance. Source: CA appendix 2022 · page 55 ↗