Le Vau Gymnasium - Subsidence studies

In 2022, the City of Paris budgeted €89k for "Le Vau Gymnasium - Subsidence studies" (, 20th arrondissement). Source: City of Paris, localised investments in the administrative account, data as of 9 February 2026.

Illustration générique gymnase municipal
Illustration
© Mbzt

Technical studies on the structure of Le Vau Gymnasium. In-depth technical studies to analyse ground movements under the building. These diagnostics are essential to define future consolidation works needed.

Gym · Other

89k €
voted in the 2022 budget
20th arrondissement · 30th project of 44 that year

The companies working on it

Contracts matched automatically to this project: check each contract’s object. Click a line to open the contract.

AVELIALot 1-assistance à maîtrise d’ouvrage Réalisation Etudes et Projets Réseau Wifi
2022 · confirmed
3.5€M
IFOPEtudes Quantitat./qualitat. Actions et Politiques VDP
2022 · confirmed
2.7€M
AVELIALot 2-assistance à maîtrise d’ouvrage Réalisation Etudes et Projets Tres Haut Debit
2022 · confirmed
2.5€M
MICHEL GUTHMANN ARCHITECTEMétropole du Grand Paris MS N°2-lot 1: assistance à maîtrise d’ouvrage Etudes Prealables/strateg.environn.
2022 · confirmed
655k €
PARTICULESMétropole du Grand Paris MS N°3-lot 1: assistance à maîtrise d’ouvrage Etudes Prealables/strateg.environn.
2022 · confirmed
278k €

Other gym projects · 2022

ZAC Saint-Vincent-de-Paul - Gymnasium creation14th1.3€MSports centre Elisabeth - Athletics-track refurbishment14th593k €Sports centre Louis Lumière - 3rd field renovation, site renovation, turf replacement20th389k €Renovating Lilas and Curial gymnasiums19th298k €

Rue Le Vau 75020 Paris · View on OpenStreetMap ↗
Amount voted, not final spending: the published accounts do not systematically give the closing balance. Source: CA appendix 2022 · page 62