$1.5M paid · $235,499 more than the recorded base amount · Agreed $1.3M
These bars total $1.8M; the figure above is $1.5M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
Sole-source is a lawful procurement path that requires a waiver or commission approval. The wording above is the register’s, unedited. See every contract awarded under Sole-source waivers →
| Supplier | Role | Attached $ |
|---|---|---|
| ANCHOR QEA, LLC | Prime | — |
| A E W ENGINEERING INCLBE | Subcontractor | $256,500 |
| BOUDREAU ASSOCIATION LLCLBE | Subcontractor | $61,192 |
| MIKE O'DELL SURVEYSLBE | Subcontractor | $48,000 |
| NORTH TOWER ENVIRONMENTAL INCLBE | Subcontractor | $40,000 |
| EUROFINS CALSCIENCE, INC. | Subcontractor | $35,500 |
| SAPERE ENVIRONMENTAL LLCLBE | Subcontractor | $13,293 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.