2019-40-FHWA
SAN FRANCISCO BICYCLE COALITION · MTA Municipal Transprtn Agncy
Agreed
$1.1M
Paid
$769,394
69% of agreed
Remaining (calculated)
$342,662
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $336,484
These bars total $1.0M; the figure above is $769,394. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
Payment detail begins FY2018 ⓘ
The deal
Contract term
September 23, 2019August 31, 2023
Term ended
Recorded purchasing authority
Purchasing authority, verbatim
MUNICIPAL TRANSPORATION AGENCY AUTHORITY - SOLE SOURCESole-source is a lawful procurement path that requires a waiver or commission approval. The wording above is the register’s, unedited. See every contract awarded under Sole-source waivers →
Sources
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)