CLP Geysers RA 182
CALPINE ENERGY SERVICES LP · PUC Public Utilities Commsn
Agreed
$30.2M
Paid
$14.9M
49% of agreed
Remaining (calculated)
$15.4M
register totals don’t reconcile ⓘ
Type
Rents & other non-purchasing agreements
Paid against the agreed ceiling
49% of the agreed amount paid · $15.4M of the agreed amount not yet paid
January 1, 2019December 31, 2029
Term running
Payments per fiscal year
Largest year: $3.6M · dashed = fiscal year not closed yet
Payment detail begins FY2018 ⓘ
Sources
- Contract number
- 1000020547
- Department
- PUC Public Utilities Commsn
- Purchasing authority
- ADMIN CODE 21.04(A)(6)-DIRECT PURCHASE BY GENERAL MANAGER OF PUC · Other special authorities
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)