CMSS Disaster Response Facility
HOLLINS CONSULTING INC · DPW GSA - Public Works
Agreed
$450,000
Paid
$126,934
28% of agreed
Remaining (calculated)
$323,066
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $91,928 · dashed = fiscal year not closed yet
Payment detail begins FY2018 ⓘ
The deal
Contract term
July 27, 2022February 6, 2028
Term running
Recorded purchasing authority
Purchasing authority, verbatim
TERM CONTRACT PROFSERV-BID, ENVIRONMENTAL CONSULTINGProject team
| Supplier | Role | Attached $ |
|---|---|---|
| HOLLINS CONSULTING INCLBE | Prime | — |
| STANTEC CONSULTING SERVICES INC | Subcontractor | $350,000 |
| SALIMI CONSTRUCTION MANAGEMENTLBE | Subcontractor | $100,000 |
| JOE HILL CONSULTING ENGINEERSLBE | Subcontractor | $70,000 |
| Contigo CommunicationsLBE | Subcontractor | $30,000 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.