Ocn Beach Clmte Chnge Adpt
MINERVA CONSTRUCTION INC · PUC Public Utilities Commsn
Agreed
$2.8M
Paid
$1.6M
59% of agreed
Remaining (calculated)
$1.1M
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $590,583
These bars total $932,065; the figure above is $1.6M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
Payment detail begins FY2018 ⓘ
The deal
Contract term
October 26, 2021June 30, 2027
Term running
Recorded purchasing authority
Purchasing authority, verbatim
CONSTRUCTION SERVICESProject team
| Supplier | Role | Attached $ |
|---|---|---|
| MINERVA CONSTRUCTION INCLBE | Prime | — |
| RONAN CONSTRUCTION, INC.LBE | Subcontractor | $650,000 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.