1308R L Taraval Improvemen
Agreed
$65.2M
Paid
$63.2M
97% of agreed
Remaining (calculated)
$2.0M
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $37.3M · dashed = fiscal year not closed yet
These bars total $64.8M; the figure above is $63.2M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
Payment detail begins FY2018 ⓘ
The deal
Contract term
November 9, 2021December 31, 2027
Term running
Recorded purchasing authority
Purchasing authority, verbatim
CONSTRUCTION SERVICESSources
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)