job order contract-90 General Engineering (A-Licen)
GSW Construction Inc. · PUC Public Utilities Commsn
Register title: “PUC JOC-90 Gnrl Engi (A-Licen)”
Signed by Public Utilities Commsn
$7.0M paid · $2.8M more than the recorded base amount · Agreed $4.3M
These bars total $4.9M; the figure above is $7.0M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
| Supplier | Role | Attached $ |
|---|---|---|
| GSW Construction Inc. | Prime | — |
| Liffey Electric, Inc.LBE | Subcontractor | $500,000 |
| GROUND COVER LANDSCAPING INCLBE | Subcontractor | $300,000 |
| GECMS, IncLBE | Subcontractor | $200,000 |
| ON THE LEVEL CONCRETELBE | Subcontractor | $200,000 |
| CMC TRAFFIC CONTROL SPECIALISTS LLC | Subcontractor | $50,000 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.