Alameda Creek Divsn Restrn
H D R ENGINEERING INC · PUC Public Utilities Commsn
Register title: “PUC Alameda Creek Divsn Restrn”
Signed by Public Utilities Commsn
Agreed
$600,000
Paid
$451,918
75% of agreed
Remaining (calculated)
$148,082
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $244,468 · dashed = fiscal year not closed yet
These bars total $419,785; the figure above is $451,918. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
Payment detail begins FY2018 ⓘ
The deal
Contract term
April 27, 2023April 26, 2027
Term running
Recorded purchasing authority
Purchasing authority, verbatim
TERM CONTRACT PROFSERV-BID, ENVIRONMENTAL CONSULTINGProject team
| Supplier | Role | Attached $ |
|---|---|---|
| H D R ENGINEERING INC | Prime | — |
| AECOM TECHNICAL SERVICES INC | Subcontractor | $400,000 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.
Sources
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)