VL Pave Renov No.60 & SWR
Register title: “PW VL Pave Renov No.60 & SWR”
ContractorPRECISION ENGINEERING INC
LBE
Agreed
$8.6M
Paid
$7.6M
88% of agreed
Remaining (calculated)
$996,586
register totals don’t reconcile ⓘ
Type
Construction
Paid against the agreed ceiling
88% of the agreed amount paid · $996,586 of the agreed amount not yet paid
July 20, 2023September 30, 2026
Term running
Payments per fiscal year
Largest year: $6.0M · dashed = fiscal year not closed yet
Payment detail begins FY2018 ⓘ
Project team
| Supplier | Role | Attached $ |
|---|---|---|
| PRECISION ENGINEERING INCLBE | Prime | — |
| ROADWAY CONSTRUCTION INCLBE | Subcontractor | $2.6M |
| BAYTECH ENGINEERING, INC.LBE | Subcontractor | $171,300 |
| M HERNANDEZ CONSTRN DBA HERNANDEZ ENGRNGLBE | Subcontractor | $60,000 |
| PROFESSIONAL ASBESTOS & LEAD SERVICES | Subcontractor | $15,000 |
| RELIANCE ENGINEERING INCLBE | Subcontractor | $15,000 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.
Sources
- Contract number
- 1000030008
- Department
- DPW Public Works
- Purchasing authority
- CONSTRUCTION SERVICES · Competitive bid
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)