Register title: “PUC TechSrvsRnwAdvceEngryGentn”
Signed by Public Utilities Commsn
Agreed
$25,232
Paid
$1.4M
more than the recorded base
Remaining (calculated)
$0
The money
Paid against the agreed amount
$1.4M paid · $1.3M more than the recorded base amount · Agreed $25,232
Payments per fiscal year
Largest year: $715,232 · dashed = fiscal year not closed yet
These bars total $715,232; the figure above is $1.4M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
Payment detail begins FY2018 ⓘ
The deal
Contract term
December 7, 2023December 6, 2028
Term running
Recorded purchasing authority
Purchasing authority, verbatim
TERM CONTRACT PROFSERV-BID, ENVIRONMENTAL CONSULTINGProject team
| Supplier | Role | Attached $ |
|---|---|---|
| NV5 | Prime | — |
| BLYMYER ENGINEERS, INC. | Subcontractor | $202,000 |
| Maffei Structural EngineeringLBE | Subcontractor | $170,000 |
| Salas O'Brien | Subcontractor | $145,200 |
| KNN PUBLIC FINANCE LLC | Subcontractor | $76,800 |
| JOE HILL CONSULTING ENGINEERSLBE | Subcontractor | $52,000 |
| LEE INCORPORATEDLBE | Subcontractor | $44,000 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.
Sources
- Dataset
- Supplier Contracts
- This contract in the source