Register title: “PUC As-Needed ProjectMngntSrvs”
Signed by Public Utilities Commsn
Agreed
$3.0M
Paid
$1.1M
38% of agreed
Remaining (calculated)
$1.9M
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $771,651 · dashed = fiscal year not closed yet
These bars total $1.2M; the figure above is $1.1M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
Payment detail begins FY2018 ⓘ
The deal
Contract term
December 12, 2023December 11, 2028
Term running
Recorded purchasing authority
Purchasing authority, verbatim
TERM CONTRACT PROFSERV-BID, ENVIRONMENTAL CONSULTINGProject team
| Supplier | Role | Attached $ |
|---|---|---|
| LEE INCORPORATED | Prime | — |
| SRT CONSULTANTSLBE | Subcontractor | $950,000 |
| MCGOVERN MCDONALD ENGINEERSLBE | Subcontractor | $475,000 |
| CHAVES & ASSOCIATESLBE | Subcontractor | $332,500 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.
Sources
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)