JOC-108 Gnrl Eng (A-Licen)
ANVIL BUILDERS INC · PUC Public Utilities Commsn
JOC-108 Gnrl Eng (A-Licen)
Register title: “PUC JOC-108 Gnrl Eng (A-Licen)”
ContractorANVIL BUILDERS INC
Agreed
$6.3M
Paid
$3.6M
56% of agreed
Remaining (calculated)
$2.7M
register totals don’t reconcile ⓘ
Type
Construction — change orders (unilateral)
Paid against the agreed ceiling
56% of the agreed amount paid · $2.7M of the agreed amount not yet paid
September 24, 2024September 23, 2029
Term running
Payments per fiscal year
Largest year: $2.3M · dashed = fiscal year not closed yet
Payment detail begins FY2018 ⓘ
Project team
| Supplier | Role | Attached $ |
|---|---|---|
| ANVIL BUILDERS INC | Prime | — |
| Liffey Electric, Inc.LBE | Subcontractor | $300,000 |
| DR Traffic ControlLBE | Subcontractor | $225,000 |
| ARBORIST NOW INCLBE | Subcontractor | $150,000 |
| Camajani TruckingLBE | Subcontractor | $150,000 |
| R&S CONSTRUCTION MANAGEMENT INCLBE | Subcontractor | $150,000 |
| WATERTIGHT RESTORATION INCLBE | Subcontractor | $150,000 |
| C&N Reinforcing, Inc.LBE | Subcontractor | $82,500 |
| Total Traffic Control, Inc.LBE | Subcontractor | $0 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.
Sources
- Contract number
- 1000034336
- Department
- PUC Public Utilities Commsn
- Purchasing authority
- CONSTRUCTION SERVICES · Competitive bid
- Dataset
- Supplier Contracts
- This contract in the source