VL Pave Renov NO.67B & Sewer
Michael O'Shaughnessy Construction Inc · DPW Public Works
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $4.1M · dashed = fiscal year not closed yet
These bars total $4.1M; the figure above is $3.7M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
Payment detail begins FY2018 ⓘ
The deal
Contract term
October 28, 2024September 27, 2026
Term running
Recorded purchasing authority
Purchasing authority, verbatim
CONSTRUCTION SERVICESProject team
| Supplier | Role | Attached $ |
|---|---|---|
| Michael O'Shaughnessy Construction IncLBE | Prime | — |
| ROADWAY CONSTRUCTION INCLBE | Subcontractor | $1.9M |
| RELIANCE ENGINEERING INCLBE | Subcontractor | $993,000 |
| BAY AREA LIGHTWORKS INCLBE | Subcontractor | $92,000 |
| Crana Trucking IncLBE | Subcontractor | $30,000 |
| Sullivan's Concrete Sawing IncLBE | Subcontractor | $30,000 |
| DR Traffic ControlLBE | Subcontractor | $10,000 |
| Daly Pipelines IncLBE | Subcontractor | $10,000 |
+ 2 more on the team
| CRANA TRUCKING | Subcontractor | $0 |
| CRANA TRUCKINGLBE | Subcontractor | $0 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.