4th St Bulbouts (Rebid)
Register title: “PW 4th St Bulbouts (Rebid)”
ContractorPRECISION ENGINEERING INC
LBE
Agreed
$1.1M
Paid
$1.9M
exceeds agreed — modifications accumulate
Remaining (calculated)
$0
register totals don’t reconcile ⓘ
Type
Construction
Paid against the agreed ceiling
$1.9M paid · $824,029 over the agreed amount · Agreed $1.1M
December 11, 2024September 30, 2026
Term running
Payments per fiscal year
Largest year: $1.1M · dashed = fiscal year not closed yet
Payment detail begins FY2018 ⓘ
Project team
| Supplier | Role | Attached $ |
|---|---|---|
| PRECISION ENGINEERING INCLBE | Prime | — |
| BAYTECH ENGINEERING, INC.LBE | Subcontractor | $353,800 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.
Sources
- Contract number
- 1000035085
- Department
- DPW Public Works
- Purchasing authority
- CONSTRUCTION SERVICES · Competitive bid
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)