Register title: “PW AN Enviro Pln Svcs 2024”
Signed by Public Works
Agreed
$570,000
Paid
$272,428
48% of agreed
Remaining (calculated)
$297,572
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $363,481 · dashed = fiscal year not closed yet
These bars total $363,481; the figure above is $272,428. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
Payment detail begins FY2018 ⓘ
The deal
Contract term
February 13, 2025March 24, 2030
Term running
Recorded purchasing authority
Purchasing authority, verbatim
TERM CONTRACT PROFSERV-BID, ENVIRONMENTAL CONSULTINGProject team
| Supplier | Role | Attached $ |
|---|---|---|
| TRC SOLUTIONS INC | Prime | — |
| A E W ENGINEERING INCLBE | Subcontractor | $330,000 |
| ARCHEO-TEC | Subcontractor | $20,000 |
| GARAVAGLIA ARCHITECTURE INCLBE | Subcontractor | $20,000 |
| Pacific Legacy, Inc. | Subcontractor | $20,000 |
| CHS CONSULTING GROUP | Subcontractor | $10,000 |
| INTEGRAL CONSULTING INC. | Subcontractor | $10,000 |
| PAGE & TURNBULL INC | Subcontractor | $10,000 |
+ 1 more on the team
| WILSON, IHRIG & ASSOCIATES, INC. | Subcontractor | $10,000 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.
Sources
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)