Register title: “INFRASTRUCTURE SERVING AMADOR”
Signed by Port
Agreed
$7.4M
Paid
$6.5M
87% of agreed
Remaining (calculated)
$937,028
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $3.9M · dashed = fiscal year not closed yet
These bars total $4.1M; the figure above is $6.5M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
Payment detail begins FY2018 ⓘ
The deal
Contract term
February 18, 2025March 31, 2027
Term running
Recorded purchasing authority
Purchasing authority, verbatim
CONSTRUCTION SERVICESProject team
| Supplier | Role | Attached $ |
|---|---|---|
| JMB CONSTRUCTION INC | Prime | — |
| CMC TRAFFIC CONTROL SPECIALISTS LLC | Subcontractor | $514,000 |
| BAYTECH ENGINEERING, INC. | Subcontractor | $498,765 |
| LONE STAR LANDSCAPE, INC. | Subcontractor | $489,590 |
| A1 TRUCKING SVS, INC. | Subcontractor | $425,000 |
| ROADWAY CONSTRUCTION INC | Subcontractor | $272,855 |
| RK Engineering INC | Subcontractor | $201,000 |
| STROER & GRAFF, INC. | Subcontractor | $118,016 |
+ 5 more on the team
| REDWOOD PAINTING CO INC | Subcontractor | $101,960 |
| PACIFIC BORING | Subcontractor | $99,858 |
| ALTA GROUP, INC. | Subcontractor | $72,000 |
| H & R UNDERGROUND | Subcontractor | $20,000 |
| BAILEY FENCE COMPANY INC | Subcontractor | $16,700 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.