AN Env Consulting Service 2025 MLBE
A E W ENGINEERING INC · DPW Public Works
Agreed
$1.0M
Paid
$130,297
13% of agreed
Remaining (calculated)
$874,703
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $195,504 · dashed = fiscal year not closed yet
These bars total $195,504; the figure above is $130,297. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
Payment detail begins FY2018 ⓘ
The deal
Contract term
April 10, 2025July 24, 2030
Term running
Recorded purchasing authority
Purchasing authority, verbatim
TERM CONTRACT PROFSERV-BID, ENVIRONMENTAL CONSULTINGProject team
| Supplier | Role | Attached $ |
|---|---|---|
| A E W ENGINEERING INCLBE | Prime | — |
| ASBESTOS TEM LABORATORIES INC | Subcontractor | $75,000 |
| MCCAMPBELL ANALYTICAL INC | Subcontractor | $75,000 |
| NEWFIELDS COMPANIES LLC | Subcontractor | $75,000 |
| PITCHER DRILLING CO | Subcontractor | $75,000 |
| TRC SOLUTIONS INC | Subcontractor | $75,000 |
| SCA ENVIRONMENTAL INCLBE | Subcontractor | $60,000 |
| WILSON, IHRIG & ASSOCIATES, INC. | Subcontractor | $45,000 |
+ 1 more on the team
| SWCA ENVIRONMENTAL CONSULTANTS | Subcontractor | $15,000 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.
Sources
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)