Register title: “UASI BATEP RFP CCS 25-27”
Signed by Emergency Management
Agreed
$373,505
Paid
$316,455
85% of agreed
Remaining (calculated)
$57,050
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $234,545 · dashed = fiscal year not closed yet
These bars total $370,405; the figure above is $316,455. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
Payment detail begins FY2018 ⓘ
The deal
Contract term
May 16, 2025May 21, 2027
Term running
Recorded purchasing authority
Purchasing authority, verbatim
NON-PURCHASINGSources
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)