AN SI & Testing Services 4
APPLIED MATERIALS & ENGINEERING INC · DPW Public Works
Register title: “PW AN SI & Testing Svcs 4”
Signed by Public Works
Agreed
$1.4M
Paid
$6,237
0% of agreed
Remaining (calculated)
$1.4M
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $6,237 · dashed = fiscal year not closed yet
Payment detail begins FY2018 ⓘ
The deal
Contract term
July 24, 2025August 12, 2030
Term running
Recorded purchasing authority
Purchasing authority, verbatim
TERM CONTRACT PROFSERV-BID, ENVIRONMENTAL CONSULTINGProject team
| Supplier | Role | Attached $ |
|---|---|---|
| APPLIED MATERIALS & ENGINEERING INC | Prime | — |
| ROLLO & RIDLEY INCLBE | Subcontractor | $160,000 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.
Sources
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)