Agreed
$1.2M
Paid
$26,374
2% of agreed
Remaining (calculated)
$1.2M
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $39,781 · dashed = fiscal year not closed yet
These bars total $39,781; the figure above is $26,374. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
Payment detail begins FY2018 ⓘ
The deal
Contract term
September 11, 2025September 23, 2030
Term running
Recorded purchasing authority
Purchasing authority, verbatim
TERM CONTRACT PROFSERV-BID, ENVIRONMENTAL CONSULTINGProject team
| Supplier | Role | Attached $ |
|---|---|---|
| SCA ENVIRONMENTAL INCLBE | Prime | — |
| CELANALYTICAL INCLBE | Subcontractor | $224,000 |
| ANALYTICAL LABS SAN FRANCISCO INCLBE | Subcontractor | $208,000 |
| A E W ENGINEERING INCLBE | Subcontractor | $64,000 |
| ASBESTOS TEM LABORATORIES INC | Subcontractor | $16,000 |
| EMSL Analytical, Inc. | Subcontractor | $16,000 |
| EUROFINS BUILT ENVIRONMENT TESTING WEST | Subcontractor | $16,000 |
| KM 106 Construction Inc.LBE | Subcontractor | $16,000 |
+ 2 more on the team
| MCCAMPBELL ANALYTICAL INC | Subcontractor | $16,000 |
| SPECIAL T MESSENGER & DELIVERY SVC COLBE | Subcontractor | $16,000 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.
Sources
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)