Agreed
$1.1M
Paid
$110,300
10% of agreed
Remaining (calculated)
$1.0M
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $134,470 · dashed = fiscal year not closed yet
These bars total $134,470; the figure above is $110,300. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
Payment detail begins FY2018 ⓘ
The deal
Contract term
September 15, 2025October 6, 2030
Term running
Recorded purchasing authority
Purchasing authority, verbatim
TERM CONTRACT PROFSERV-BID, ENVIRONMENTAL CONSULTINGProject team
| Supplier | Role | Attached $ |
|---|---|---|
| ENVIROSURVEY INCLBE | Prime | — |
| MILLENNIUM CONSULTING ASSOCIATES | Subcontractor | $128,000 |
| TERRACON CONSULTANTS INC | Subcontractor | $120,000 |
| Sierra Aqua Technologies, Inc | Subcontractor | $80,000 |
| EMSL Analytical, Inc. | Subcontractor | $64,000 |
| MCCAMPBELL ANALYTICAL INC | Subcontractor | $40,000 |
| CELANALYTICAL INCLBE | Subcontractor | $32,000 |
| EUROFINS BUILT ENVIRONMENT TESTING WEST | Subcontractor | $16,000 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.
Sources
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)