Var Loc Sewer Inspec NO 3
PIPE AND PLANT SOLUTIONS INC · PUC Public Utilities Commsn
Register title: “PUC VAR LOC SEWER INSPEC NO 3”
Signed by Public Utilities Commsn
Agreed
$4.8M
Paid
$1.8M
38% of agreed
Remaining (calculated)
$3.0M
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $2.1M · dashed = fiscal year not closed yet
These bars total $2.1M; the figure above is $1.8M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
Payment detail begins FY2018 ⓘ
The deal
Contract term
December 3, 2025April 4, 2027
Term running
Recorded purchasing authority
Purchasing authority, verbatim
CONSTRUCTION SERVICESProject team
| Supplier | Role | Attached $ |
|---|---|---|
| PIPE AND PLANT SOLUTIONS INC | Prime | — |
| M HERNANDEZ CONSTRN DBA HERNANDEZ ENGRNGLBE | Subcontractor | $255,152 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.
Sources
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)