Water Sewer Replacement 3RD to Griffi
Agreed
$11.0M
Paid
$0
0% of agreed
Remaining (calculated)
$11.0M
The money
Paid against the agreed amount
Payments per fiscal year
No voucher-level payment detail for this contract (detail begins FY2018 — earlier or indirect payments don’t appear).
Payment detail begins FY2018 ⓘ
The deal
Contract term
March 4, 2026May 19, 2028
Term running
Recorded purchasing authority
Purchasing authority, verbatim
CONSTRUCTION SERVICESProject team
| Supplier | Role | Attached $ |
|---|---|---|
| M SQUARED CONSTRUCTION INCLBE | Prime | — |
| RONAN CONSTRUCTION, INC.LBE | Subcontractor | $1.7M |
| Basset EngineeringLBE | Subcontractor | $706,500 |
| CRANA TRUCKINGLBE | Subcontractor | $300,000 |
| SAK CONSTRUCTION OF CA LP | Subcontractor | $136,870 |
| Robotic Sewer Solutions, Inc. | Subcontractor | $54,400 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.
Sources
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)