Cherry Vlly,Eleanor DamImp
Njirich & Sons, Inc. · PUC Public Utilities Commsn
Agreed
$7.4M
Paid
$0
0% of agreed
Remaining (calculated)
$7.4M
The money
Paid against the agreed amount
Payments per fiscal year
No voucher-level payment detail for this contract (detail begins FY2018 — earlier or indirect payments don’t appear).
Payment detail begins FY2018 ⓘ
The deal
Contract term
April 29, 2026July 27, 2027
Term running
Recorded purchasing authority
Purchasing authority, verbatim
CONSTRUCTION SERVICESProject team
| Supplier | Role | Attached $ |
|---|---|---|
| Njirich & Sons, Inc.LBE | Prime | — |
| TPA CONSTRUCTION INC. | Subcontractor | $942,360 |
| Mountain Methods, Inc.LBE | Subcontractor | $800,000 |
| JB Excavation IncLBE | Subcontractor | $400,000 |