Contractor for FCEC Flooding Repairs: Elec & Controls ITT

In 2019, the City of Vancouver awarded “Contractor for FCEC Flooding Repairs: Elec & Controls ITT” (invitation to tender PS20190744) to Ross Morrison Electrical Ltd for $581k. 2 vendors responded; offers ranged from $581k to $681k. Source: City of Vancouver open data, Awarded contracts, data as of 23 July 2026.

$581k
awarded on August 8, 2019
bid PS20190744

The competition

Bids on this competition2bids
Invitation to tender, 2019: median bids32 competitions · 4 with a single bid4bids

The offers

The awarded offer was the lowest of the 2 priced offers.

Ross Morrison Electrical LtdAwarded$581kSasco Contractors LtdNot awarded$681k
About these figures

Every response the City published for this competition, awarded first, then by price.

Awarded amounts are what the City agreed at award. What it later paid each supplier is published only in the annual Statement of Financial Information.