Contractor Services for Utility Cut Repairs in Gastown - Phase 1a
In 2025, the City of Vancouver awarded “Contractor Services for Utility Cut Repairs in Gastown - Phase 1a” (request for quotes PS20230345-ENG-RFQ) to Formline Construction Ltd. for $385k. 2 vendors responded; offers ranged from $385k to $670k. Source: City of Vancouver open data, Awarded contracts, data as of 23 July 2026.
$385k
awarded on November 25, 2025
The competition
Bids on this competition2bids
Request for quotes, 2025: median bids13 competitions · 6 with a single bid2bidsThe offers
The awarded offer was the lowest of the 2 priced offers.
Formline Construction Ltd.Awarded$385kJack Cewe Construction Ltd.Not awarded$670kAbout these figures
Every response the City published for this competition, awarded first, then by price.
Awarded amounts are what the City agreed at award. What it later paid each supplier is published only in the annual Statement of Financial Information.