2023-2026 Rain & Ground Water monitoring
“2023-2026 Rain & Ground Water monitoring” is a City of Vancouver capital program (Water, sewers & drainage) in the budgets 2023–2026; its 2023 capital expenditure budget is $100k.
Source: City of Vancouver open data, capital budgets.
$100k
capital expenditure budget, 2023
Capital expenditure budget, by budget year
$100k in 2023 · $2.7M in 2026
Click a year to see its amount.
How its 2023 new budget of $250k is funded
Pay-as-you-go (tax and fees)$125k
Borrowing (debt)$125k
About these figures
A program is followed across budget years by its name; where a file spells it differently, a reviewed list joins the spellings. A program opened again under a new plan period is a separate fiche.