The City of Vancouver's 2024 capital expenditure budget puts $150M into streets, 19% of the year; the largest program is “Granville North Loops”.

Source: City of Vancouver open data, capital budget 2024.

$150M
capital expenditure budget, 2024
19% of the year · $73.4M new multi-year budget · number 2 of 13 services in 2024

By year, 2021–2026

$109M in 2021 · $189M in 2026

Click a year to see its amount.

Its programs, 2024

Granville North LoopsBuilding a resilient network$15.0MGranville Bridge structural steel repairs & recoating (Phase 2)Building a resilient network$11.0MGranville Bridge GreenwaysBuilding a resilient network$8.0MCambie Bridge - SeismicBuilding a resilient network$7.0MDesign for Robson & Alberni Street ImprovementsSupporting public life$5.6M2023-2026 MRN (Major Road Network) rehabilitationBuilding a resilient network$5.6M2019-2022 Metered Parking programSupporting public life$5.3M2023-2026 Arterial Road rehabilitationBuilding a resilient network$3.8M
Show 82 more2019-2022 New SidewalksImproving mobility$3.4M2023-2026 Signal rehabilitationBuilding a resilient network$3.3MViaducts Removal/Northeast False Creek RedevelopmentBuilding a resilient network$3.0MStreet Lighting & Pole - rehabilitationBuilding a resilient network$2.9MUnderground Street Lighting ConduitsBuilding a resilient network$2.8MGastown/Water Street - Near term repairs & reconstructionSupporting public life$2.7M2023-2026 Local Roads rehabilitationBuilding a resilient network$2.5MDrake Green Complete Street ImprovementsImproving mobility$2.5M2023-2026 Replacement of Vehicles & Equipment - StreetsBuilding a resilient network$2.5MNew Active Transportation improvementsImproving mobility$2.4MPlanning and research for Equity Related InitiativesSupporting public life$2.3M2023-2026 Sidewalks rehabilitationBuilding a resilient network$2.2MWest End Active Transportation ImprovementsSupporting public life$2.2MUpgrades to Active Transportation NetworkImproving mobility$2.1MBus Operations & AccessibilityImproving mobility$2.0M2023-2026 At-Grade Rail CrossingsImproving mobility$2.0MArbutus Greenway- King Edward/ArbutusImproving mobility$2.0MClimate Emergency Response - Transportation initiativesImproving mobility$2.0MCity Wide Street Lighting LED replacementBuilding a resilient network$1.9M2023-2026 Bus transit improvementsImproving mobility$1.6M2023-2026 New SignalsBuilding a resilient network$1.6MRapid Transit - staffingImproving mobility$1.5M2023-2026 H-Frame replacementBuilding a resilient network$1.5MFixtures – Decorative/Pedestrian ScaleBuilding a resilient network$1.5MTransportation monitoringImproving mobility$1.5MTransportation safety & accessibility improvementsImproving mobility$1.5M2023-2026 Trolley Pole replacementBuilding a resilient network$1.4M2023-2026 General Bridge rehabilitation programBuilding a resilient network$1.3M2023-2026 Gathering PlacesSupporting public life$1.2M2023-2026 Transportation planning & monitoringImproving mobility$1.2M2019-2022 Underground Street Lighting ConduitsBuilding a resilient network$1.2MClimate Emergency Response - Curbside electrical power supplySupporting public life$1.2MPedestrian & Bike Signal rehabilitationBuilding a resilient network$1.2M2023-2026 Transportation Design staffingImproving mobility$1.1MSignal Communication rehabilitationBuilding a resilient network$1.1MCambie Bridge - rehabilitationBuilding a resilient network$1.0MGastown/ Water Street public space and transportation improvementsSupporting public life$933k2023-2026 Public realm electrificationSupporting public life$900k2023-2026 School programImproving mobility$900k2023-2026 Public realm EV charging infrastructureSupporting public life$800k2023-2026 Active Transportation & Complete streets - Portside GreenwayImproving mobility$792kCambie Corridor Complete Street Improvements - King Edward To 37thImproving mobility$750k2023-2026 Transportation SafetyImproving mobility$700k2019-2022 Rehabilitation of Street Pole BasesBuilding a resilient network$700k2023-2026 Equity and Cultural Redress staffingSupporting public life$680k2023-2026 Pedestrian curb rampsImproving mobility$670kElectrical Vehicle InfrastructureSupporting public life$617k2019-2022 Neighbourhood Safety ImprovementsImproving mobility$600k2019-2022 LED Fixture Electrification SensorsBuilding a resilient network$600k2019-2022 Street Activities (Renewal)Supporting public life$584kLight Fixture Arm - rehabilitationBuilding a resilient network$520k2022 Climate Emergency Action dedicated funding - Transit Priority CorridorImproving mobility$500kNew Active Transportation improvements- Drake streetImproving mobility$500kTraffic Signal Controller replacementBuilding a resilient network$500k2019-2022 Zero Fatalities & Serious Injuries programImproving mobility$500k2019-2022 Street Light Fixture Arm rehabilitationBuilding a resilient network$450k2023-2026 Retaining wall & slope rehabilitationBuilding a resilient network$425kFilm Power Kiosk NetworkBuilding a resilient network$400kGranville Bridge South Approach rehabilitation (Phase 1)Building a resilient network$400k2022 Climate Emergency Action dedicated funding- Slow StreetsImproving mobility$350k2023-2026 New Street LightingBuilding a resilient network$330kAccessible Public Washrooms - Charleson ParkSupporting public life$327k2023-2026 Active Transportation - Beatty StreetImproving mobility$300k2023-2026 Arterial & construction managementImproving mobility$300k2023-2026 HorticultureSupporting public life$300kBike Racks + Street FurnitureSupporting public life$300k2019-2022 Transportation Planning StudiesImproving mobility$279k2019-2022 Engineering Project Management Office (PMO) - implementationBuilding a resilient network$271kGastown Complete Street ImprovementsSupporting public life$264k2023-2026 Neighbourhood traffic management & spot improvementsImproving mobility$250kSen̓áḵw Engineering studiesBuilding a resilient network$250k2019-2022 Trolley Route ReroutingImproving mobility$250kService Panels & Kiosks - rehabilitationBuilding a resilient network$240kComfort Station renewalSupporting public life$240k2019-2022 Street Activities (New)Supporting public life$237k2023-2026 Design Investigation - Streets & StructuresBuilding a resilient network$234kTraffic Signal LED replacementBuilding a resilient network$200k2019-2022 Pedestrian Curb Ramp programImproving mobility$200kStill Creek viewing platformImproving mobility$170kWest End public space & transportation improvements: Neighbourhood ImprovementsSupporting public life$89k2019-2022 Rehabilitation of Electrical Service Panels & KiosksBuilding a resilient network$75k2022 Climate Emergency Action dedicated funding - Electric Vehicle Fleet & Electric Vehicle InfrastructureSupporting public life$54k

In the 2023–2026 Capital Plan: $652M, by sub-category

Building a resilient network33 programs$342M
Improving mobility13 programs$223M
Supporting public life13 programs$70.5M
Prior Capital Plan Items1 programs$16.2M
About these figures

Each program is listed under the service the year’s budget file gives it; a program can move from one service to another between budgets.