AIR50364 Grant Management
Accenture Infrastructure and Capital Pro · AIR Airport Commission
Signed by Airport Commission
Agreed
$5.0M
Paid
$930,885
19% of agreed
Remaining (calculated)
$4.1M
The money
Paid against the agreed amount
Payments per fiscal year
Largest year: $571,058 · dashed = fiscal year not closed yet
These bars total $972,758; the figure above is $930,885. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
Payment detail begins FY2018 ⓘ
The deal
Contract term
May 8, 2024May 7, 2029
Term running
Recorded purchasing authority
Purchasing authority, verbatim
COMPETITIVE SOLICITATIONSources
- Dataset
- Supplier Contracts
- This contract in the source
- Raw rows (JSON, data.sfgov.org)