Airport Commission
What this department buys, and from whom · department code AIR
Agreed, active today
$4.2B
$2.9B paid · 69%
Contracts active today
262
3,184 on the books all time
Suppliers under contract
214
Sole-source, active
33 / 262
Biggest suppliers, active contracts
TURNER CONSTRUCTION CO1 contract$1.7B
AUSTIN WEBCOR JV2 contracts$442.6M
HENSEL PHELPS CONSTRUCTION CO1 contract$278.1M
WALSH CONSTRUCTION COMPANY II1 contract$265.0M
SP Plus SF Joint Venture1 contract$214.9M
Alstom Transport USA Inc1 contract$208.6M
Biggest active contracts
Airport construction, project 10071.76TURNER CONSTRUCTION CO$1.7BAirport construction, project 11917.66AUSTIN WEBCOR JV · paid past ceiling$278.6MCourtyard connector construction at the AirportHENSEL PHELPS CONSTRUCTION CO · paid past ceiling$278.1MRecycled water project at the AirportWALSH CONSTRUCTION COMPANY II$265.0MAirport parking management and operationSP Plus SF Joint Venture$214.9MAirTrain operationAlstom Transport USA Inc$208.6M
+ 6 more contracts
Airport construction: Boarding Area GAUSTIN WEBCOR JV$164.1MAirport construction: Cargo Building 720.1&GSSKANSKA USA BUILDING INC$108.7MAirport project management services, project 10071.41WCME JV$108.2MAirport construction: Cargo Building 626.1CLARK CONSTRUCTION GROUP - CALIF LP$104.1MAIR50303 Shuttle Bus ServicesSFO HOTEL SHUTTLE INC$72.6MAIR50276 Curbside ManagementSP PLUS CORPORATION$41.4M
Showing the 12 biggest of 262 active contracts · search them all →
Elsewhere on this department
Contracts are commitments to suppliers; the budget is what the department is appropriated and spends across salaries, materials and everything else. The two do not add up and answer different questions. Airport Commission’s budget →
Source
Every figure is a sum over the supplier-contract register, grouped on its own department code AIR. Supplier Contracts ↗