Architectural and Engineering Services for East Wing Deconstruction, Design, and Remedial Work
In 2015, the City of Vancouver awarded “Architectural and Engineering Services for East Wing Deconstruction, Design, and Remedial Work” (request for proposals PS20140023) to DA Architects + Planners for $189k. 10 vendors responded. Source: City of Vancouver open data, Awarded contracts, data as of 23 July 2026.
$189k
awarded on January 28, 2015
The competition
Bids on this competition10bids
Request for proposals, 2015: median bids53 competitions · 9 with a single bid3bidsThe offers
DA Architects + PlannersAwarded$189kAbbarch Architecture IncNot awardedno priceArchitecture49 Inc.Not awardedno priceBruce Carscadden Architect IncNot awardedno priceDys ArchitectureNot awardedno priceFlow Consulting Group IncNot awardedno priceIredale Group ArchitectureNot awardedno priceMusson Cattell Mackey PartnershipNot awardedno pricePUBLIC DesignNot awardedno priceThibodeau Architecture + DesignNot awardedno priceAbout these figures
Every response the City published for this competition, awarded first, then by price.
Awarded amounts are what the City agreed at award. What it later paid each supplier is published only in the annual Statement of Financial Information.