Vendor
Matcon Excavation And Shoring Ltd
Matcon Excavation And Shoring Ltd won 0 of the 2 competitions it entered between 2016 and 2019.
Source: City of Vancouver open data, Awarded contracts, data as of 23 July 2026.
2
competitions entered, none won
What the City paid
Matcon Excavation and Shoring Ltdpaid by the City, 2016–2020$139kCompetitions
For a competition it lost, the amount is its offer.
Vancouver Landfill Phase 4 Closure - Contractor PrequalificationOffer, not awarded · Pre-qualification · 2019no priceDesign-Build of Shotcrete Wall at Empire FieldsOffer, not awarded · Request for proposals · 2016no priceAbout these figures
Vendor name as published in the City of Vancouver's awarded-contracts register.
The same organisation in the City's payment schedules (payments over $25,000), where the names match.
Awarded amounts are what the City agreed at award. What it later paid each supplier is published only in the annual Statement of Financial Information.