Entrée nord du complexe sportif des Sept Fonts et construction d’une salle polyvalente

€462k
maximum contract amount over 3 years — what was paid on it is not published
Signed on 4 January 2024 · running until about January 2027 · 3 yrs
Ongoing4 Jan 2027

That is at most ~€154k a year on average: a maximum too.

Company selected

Charles et MouyssetTravaux de charpente · registered office Rodez (12000) · headcount 10 to 19 employees · SIREN 426680054

The competition

3 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 18 by amount of the 116 contracts Agde published for 2024. It belongs to the policy Culture, sport and youth.

Other contracts of Charles et Mouysset in Agde

Construction salle polyvalente2024 · maximum over 3 years462€kCréation d’une halle sportive : charpente bois et bardage2021 · maximum over 4 months1.2€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Clause sociale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.