Public contracts of Aix-les-Bains · 2019 · Construction and buildings

Travaux de mise en accessibilité PMR du groupe scolaire de Choudy

Maçonnerie · Démolition

€36k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 17 January 2019 · ended around April 2020 · 15 months

That is at most ~€29k a year on average: a maximum too.

Company selected

SA PiantoniTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Saint-Baldoph (73190) · SIREN 401033519

Number 39 by amount of the 55 contracts Aix-les-Bains published for 2019. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.