Public contracts of Albertville · 2019 · Professional services

Maîtrise d’oeuvre extension du bâtiment des services techniques, réhabilitation et organisation

€97k
maximum contract amount over 7 months — what was paid on it is not published
Signed on 12 February 2019 · ended around September 2019 · 7 months

Company selected

Imhotep Architectes Rhone AlpesActivités d'architecture · registered office Champagny-En-Vanoise (73350) · SIREN 348220880

Number 22 by amount of the 84 contracts Albertville published for 2019.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.