Skip to main content

Public contracts of Albertville · 2019 · Construction and buildings

Rejointoiement des façades

Tour sarrasine

€58k
maximum contract amount over 3 years — what was paid on it is not published
Signed on 31 October 2019 · ended around October 2022 · 3 yrs

That is at most ~€19k a year on average: a maximum too.

Company selected

ComteTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Champdieu (42600) · headcount 50 to 99 employees · SIREN 885750521

Number 42 by amount of the 84 contracts Albertville published for 2019.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.