Travaux de rénovation, de modernisation, de dépannage et maintenance des ascenseurs et monte-charges
That is at most ~€47k a year on average: a maximum too.
Company selected
Orona Ouest Nord (Ascenseurs Alti Lift)Autres travaux d'installation n.c.a. · registered office La Chapelle-Des-Fougeretz (35520) · headcount 100 to 199 employees · SIREN 414672717Number 5 by amount of the 22 contracts Alençon published for 2026.
Contract details (procedure, price, amendments, lots)
Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds
Framework agreement : yes: orders follow, the amount is a ceiling
Price : Unitaire
Published amendments : none
Subcontracting declared : no
The 2 lots : 100 €k · 86 €k
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.