Public contracts of Alfortville · 2023 · Construction and buildings

Extension de l’école maternelle Louise Michel : démolition, gros œuvre, façades

€1.4M
maximum contract amount over 13 months — what was paid on it is not published
Signed on 26 April 2023 · ended around May 2024 · 13 months

That is at most ~€1.3M a year on average: a maximum too.

Company selected

Titulaire sans SIRET

The competition

20 bids received

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 2 by amount of the 42 contracts Alfortville published for 2023. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

The filing gives no SIRET for the contractor: since we cannot check it is not a person, the name is not published.

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.