Réfection et modernisation de l’éclairage public

€1M
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 24 September 2026 · running until about September 2030 · 4 yrs
Ongoing24 Sept 2030

That is at most ~€250k a year on average: a maximum too.

Company selected

Cegelec Infras Sud-Est (Omexom)Travaux d'installation électrique dans tous locaux · registered office Vitrolles (13127) · headcount 50 to 99 employees · SIREN 537915738

The competition

4 bids received

Median for this procedure in 2026: 3 bids, across 23502 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

The largest of the 18 contracts Allos published for 2026.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Mixte

Published amendments : none

Subcontracting declared : no

Environmental considerations : Critère environnemental, Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.