Public contracts of Anglet · 2024 · Construction and buildings

Reconstruction de la maison de l’environnement du parc izadia

€58k
maximum contract amount over 13 months — what was paid on it is not published
Signed on 28 June 2024 · ended around July 2025 · 13 months

That is at most ~€53k a year on average: a maximum too.

Company selected

LorenziTravaux de peinture et vitrerie · registered office Ibos (65420) · headcount 100 to 199 employees · SIREN 317807444

The competition

3 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 81 by amount of the 104 contracts Anglet published for 2024.

Other contracts of Lorenzi in Anglet

Peintures sols souples2024 · maximum over 6 months65€kRéfection des abords extérieurs et remise en état du sous-sol intérieur…2022 · maximum over 4 months29€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 2