Skip to main content

Public contracts of Arcis-sur-Aube · 2026 · Construction and buildings

Rénovation et extension du gymnase : charpente métallique

€158k
maximum contract amount over 13 months — what was paid on it is not published
Signed on 11 May 2026 · running until about June 2027 · 13 months
Ongoing11 Jun 2027

That is at most ~€146k a year on average: a maximum too.

Company selected

Ateliers Bois et CompagnieFabrication de structures métalliques et de parties de structures · registered office Chaumont (52000) · headcount 20 to 49 employees · SIREN 845420017

The competition

2 bids received

Median for this procedure in 2026: 3 bids, across 23525 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 3 by amount of the 11 contracts Arcis-sur-Aube published for 2026.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 2

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.