Public contracts of Argonay · 2022
Refection du terrain synthetique du stade Robert ZAPPELLI
Number 2 by amount of the 14 contracts Argonay awarded in 2022.
Contract · Construction and Bâtiment · carried out in 74370
644k €
contract ceiling — what was paid on it is not published
Who won it
Mithieux TPSIREN 326520780The competition
Number of bids not published for that year: the field is only systematic from 2024.
Adapted procedure · awarded to 2 companies
Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.
The form of the contract
PriceRévisable
Published amendmentsnone
Other contracts of Mithieux TP in Argonay
1ère phase de travaux pour la rénovation énergétique et intérieure du Groupe Scolaire et sa mise en accessibilité - Installation de bâtiments modulaires provisoires sur le terrain de football2026227k€Route des Jouvenons - Aménagement et sécurisation arrêt bus Pré du Buisson202698k€Aménagement de la route des Granges2025376k€1ère phase de travaux pour la rénovation énergétique et intérieure du Groupe Scolaire et sa mise en accessibilité - Installation de bâtiments modulaires provisoires sur le terrain de football2024866k€ROUTE DES CONVERS_Amenagement et securisation de voirie2024394k€Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.