Public contracts of Asnières-sur-Seine · 2023 · Energy

Fourniture et acheminement d’électricité pour les puissances supérieures à 36 kVA, 2024-2025

€8M
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 7 July 2023 · running until about July 2027 · 4 yrs
Ongoing7 Jul 2027

That is at most ~€2M a year on average: a maximum too.

Company selected

EngieCommerce de combustibles gazeux par conduites · registered office La Garenne-Colombes (92250) · headcount 2,000 to 4,999 employees · SIREN 542107651

Amounts paid

Electricity, gas and heating: €6.1M paid by Asnières-sur-Seine in 2023, all suppliers together (its accounts). The accounts do not say what share went to Engie.

Number 2 by amount of the 61 contracts Asnières-sur-Seine published for 2023.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.