Public contracts of Asnières-sur-Seine · 2025 · Construction and buildings
Halle du marché 4 routes : gros œuvre, charpente
That is at most ~€1.7M a year on average: a maximum too.
Company selected
Briand Metal ChartresFabrication de structures métalliques et de parties de structures · registered office Les Villages Voveens (28150) · headcount 50 to 99 employees · SIREN 434621314A contract awarded to a consortium of 2 holders; above, the main holder. With it: Entreprise de Travaux Fayolle et Fils. The amount is the whole contract’s: the DECP does not publish each holder’s share.
The competition
Median for this procedure in 2025: 3 bids, across 49612 comparable contracts. Simplified procedure · awarded to 2 companies
Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.
Number 7 by amount of the 215 contracts Asnières-sur-Seine published for 2025. It belongs to the policy Streets and transport.
Contract details (procedure, price, amendments, lots)
Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds
Price : Forfaitaire
Published amendments : 4
Environmental considerations : Clause environnementale
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.