Skip to main content

Public contracts of Athis-Mons · 2019 · Construction and buildings

Construction d’un bâtiment scolaire modulaire pour le groupe scolaire Jean-Baptiste de La Salle

€596k
maximum contract amount over 3 months — what was paid on it is not published
Signed on 1 April 2019 · ended around July 2019 · 3 months

Company selected

Pref'AubConstruction d'autres bâtiments · registered office Villechetif (10410) · headcount 20 to 49 employees · SIREN 662880509

Number 3 by amount of the 40 contracts Athis-Mons published for 2019. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.