Public contracts of Bandol · 2025 · Construction and buildings

Dévoiement refoulement eau potable AVT construction stade

€92k
maximum contract amount over 3 months — what was paid on it is not published
Signed on 24 February 2025 · ended around May 2025 · 3 months

Company selected

Bronzo T.P.Construction de réseaux pour fluides · registered office La Ciotat (13600) · headcount 100 to 199 employees · SIREN 501656573

Number 37 by amount of the 49 contracts Bandol published for 2025. It belongs to the policy Culture, sport and youth.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.